  (1)   For the purposes of this Part, the transition period for a person begins on the commencement day and ends on:

  (a)   if the person lodges an application for an Australian financial services licence covering claims handling and settling services and ASIC gives the applicant notice in writing on or before 30   June 2021 that the application is granted--the last licence - processing day; or

  (b)   if the person lodges an application for an Australian financial services licence covering claims handling and settling services, the application complies with section   913A and is pending on 30   June 2021--the earlier of:

  (i)   if, after 30   June 2021, the person withdraws the application--the day on which the application is withdrawn; and

  (ii)   if, after 30   June 2021, ASIC notifies the person in writing that ASIC refuses to receive the application under subsection   1274(8)--the day on which ASIC gives that notification; and

  (iii)   if ASIC refuses to grant the person an Australian financial services licence covering claims handling and settling services--the day on which ASIC gives the person notice in writing of the refusal; and

  (iv)   the last licence - processing day; or

  (c)   if the person lodges an application for ASIC to vary the conditions on the licence to specify that claims handling and settling services are financial services that the licensee is authorised to provide and ASIC gives the applicant notice in writing on or before 30   June 2021 that the application is granted--the last licence - processing day; or

  (d)   if the person is a financial services licensee and lodges an application for ASIC to vary the conditions on the licence to specify that claims handling and settling services are financial services that the licensee is authorised to provide, the application complies with paragraph   914A(2)(b) and is pending on 30   June 2021--the earlier of:

  (i)   if, after 30   June 2021, the person withdraws the application--the day on which the application is withdrawn; and

  (ii)   if, after 30   June 2021, ASIC notifies the person in writing that ASIC refuses to receive the application under subsection   1274(8)--the day on which ASIC gives that notification; and

  (iii)   if ASIC refuses to grant the person the variation--the day on which ASIC gives the person notice in writing of the refusal; and

  (iv)   the last licence - processing day; or

  (e)   otherwise--30   June 2021.

  (2)   In this section:

"last licence-processing day" means the later of:

  (a)   31   December 2021; and

  (b)   if the Minister determines another day under subsection   (3)--that other day.

"pending" : an application is pending on a particular day if the application has been lodged on or before that day and each of the following is satisfied:

  (a)   the application has not been withdrawn by the applicant on or before that day;

  (b)   ASIC has not, on or before that day, given the applicant notice in writing that the application has been granted or refused;

  (c)   ASIC has not, on or before that day, notified that applicant in writing that ASIC refuses to receive the application under subsection   1274(8).

  (3)   The Minister may, by notifiable instrument, determine a day that is after 31   December 2021 and before 1   July 2022 to be the last licence - processing day.


AustLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback