(1) In this Chapter, structure has the same meaning as it has in the Act.
3 Foundations, earth retention works and other earthworks, including river works and sea defence works.
4 Formwork, falsework or any other structure designed or used to provide support, access or containment during construction work.
6 A dock, harbour, channel, bridge, viaduct, lagoon or dam.
7 A sewer or sewerage or drainage works.
(2) This Chapter does not apply to plant unless:
(iv) designed or used to provide support, access or containment during work in connection with construction work; or
(b) work on the plant relates to work that is carried out in connection with construction work; or
(c) the plant is fixed plant on which outage work or overhaul work that involves or may involve work being carried out by 5 or more persons conducting businesses or undertakings at any point in time.
Note: This Chapter does not apply to the manufacture of plant (see
paragraph 289(3)(a)).