Commonwealth Consolidated Regulations

[Index] [Table] [Search] [Search this Regulation] [Notes] [Noteup] [Previous] [Next] [Download] [Help]

WORK HEALTH AND SAFETY REGULATIONS 2011 - REG 311

WHS management plan--review

  (1)   The principal contractor for a construction project must review and, as necessary, revise the WHS management plan to ensure that it remains up - to - date.

Penalty:

  (a)   In the case of an individual--$3   600.

  (b)   In the case of a body corporate--$18   000.

Note:   Section   12F of the Act provides that strict liability applies to each physical element of each offence under the Act, unless otherwise stated. The reference in section   12F of the Act includes these Regulations.

  (2)   The principal contractor for a construction project must ensure, so far as is reasonably practicable, that each person carrying out construction work in connection with the project is made aware of any revision to the WHS management plan.

Penalty:

  (a)   In the case of an individual--$3   600.

  (b)   In the case of a body corporate--$18   000.

Note:   Section   12F of the Act provides that strict liability applies to each physical element of each offence under the Act, unless otherwise stated. The reference in section   12F of the Act includes these Regulations.


AustLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback