WORK HEALTH AND SAFETY REGULATIONS 2011 - REG 583

Refusal to grant major hazard facility licence--process

  (1)   If the regulator proposes to refuse to grant a major hazard facility licence, the regulator must give a written notice to the operator:

  (a)   informing the operator of the reasons for the proposed refusal; and

  (b)   advising the operator that the operator may, by a specified date (being not less than 28 days after giving the notice), make a submission to the regulator in relation to the proposed refusal.

  (2)   After the date specified in a notice under subregulation   (1), the regulator must:

  (a)   if the operator has made a submission in relation to the proposed refusal to grant the licence--consider that submission; and

  (b)   whether or not the operator has made a submission--decide whether to grant or refuse to grant the licence; and

  (c)   within 14 days after making the decision, give the operator written notice of the decision, including the reasons for the decision.