New South Wales Consolidated Regulations

[Index] [Table] [Search] [Search this Regulation] [Notes] [Noteup] [Previous] [Next] [Download] [Help]

ENVIRONMENTAL PLANNING AND ASSESSMENT REGULATION 2000 - REG 104

Notice under sections 6.6 and 6.12 of the Act of intention to commence subdivision work or erection of building

104 Notice under sections 6.6 and 6.12 of the Act of intention to commence subdivision work or erection of building

(cf clause 70 of EP[#38]A Regulation 1994)

(1) A notice given under or for the purposes of section 6.6(2)(e) or 6.12(2)(c) of the Act must contain the following information--
(a) the name and address of the person by whom the notice is being given,
(b) a description of the work to be carried out, and
(c) the address of the land on which the work is to be carried out, and
(d) the registered number and date of issue of the relevant development consent,
(e) the registered number and date of issue of the relevant construction certificate,
(f) a statement signed by or on behalf of the principal certifier to the effect that all conditions of the consent that are required to be satisfied prior to the work commencing have been satisfied,
(g) the date on which the work is intended to commence.
(2) The notice must be lodged on the NSW planning portal.