ENVIRONMENTAL PLANNING AND ASSESSMENT REGULATION 2000 - REG 111
Days occurring during consultation under National Parks and Wildlife Act 1974
111 Days occurring during consultation under National Parks and Wildlife Act
1974
(1) If-- (a) development is integrated development because, or partly because,
it requires consent under section 90 of the National Parks and Wildlife Act
1974 , and
(b) the Chief Executive of the Office of Environment and Heritage
is of the opinion that consultation with an Aboriginal person or persons, an
Aboriginal Land Council or another Aboriginal organisation concerning a relic
or Aboriginal place is required before the Chief Executive can make a decision
concerning the general terms of approval in relation to such a consent
(including whether or not the Chief Executive will grant consent),
any day
that occurs during the consultation (being a period that does not extend more
than 46 days from the date on which the development application was lodged on
the NSW planning portal) is not to be taken into consideration for the purpose
of calculating the number of days in any of the assessment periods.
(2)
Subclause (1) applies only if the consultation commences within 25 days after
the date on which the development application is forwarded to the Chief
Executive of the Office of Environment and Heritage. Note : The 25-day period
may be extended by operation of clauses 107 and 108.