ENVIRONMENTAL PLANNING AND ASSESSMENT REGULATION 2000 - REG 124AA
When work is physically commenced
124AA When work is physically commenced
(1) For the purposes of section 4.53(7) of the Act, work is not taken to have
been physically commenced merely by the doing of any one or more of the
following-- (a) creating a bore hole for soil testing,
(b) removing water or
soil for testing,
(c) carrying out survey work, including the placing of pegs
or other survey equipment,
(d) acoustic testing,
(e) removing vegetation as
an ancillary activity,
(f) marking the ground to indicate how land is to be
developed.
(2) This clause does not apply to a development consent granted
before the commencement of this clause.