ENVIRONMENTAL PLANNING AND ASSESSMENT REGULATION 2000 - REG 148J
Deemed refusal period for application for subdivision works certificate
(1) For the purposes of section 8.17(1) of the Act, a council is taken to have
made a decision to refuse to issue a subdivision works certificate if,
following an application for the certificate, the council fails to issue the
certificate within the period that ends on the day that is-- (a) if the
application is made on or before the day on which the council determines the
associated development application for the application--the last day of the
period referred to in section 8.11(1) of the Act at the end of which the
council is taken to have determined the associated development application by
refusing development consent (or refusing to modify development consent), or
(b) otherwise--28 days after the day on which the application was made.
(2)
In this clause--
"associated development application" , for an application for a subdivision
works certificate, means the development application for the development to
which the application for the subdivision works certificate relates.
AustLII: Copyright Policy
| Disclaimers
| Privacy Policy
| Feedback