ENVIRONMENTAL PLANNING AND ASSESSMENT REGULATION 2000 - REG 186O
Installation of fire sprinkler systems in facilities with 1 March 2016 as nominated completion date
186O Installation of fire sprinkler systems in facilities with 1 March 2016 as
nominated completion date
(1) If an approved provider of a facility nominated 1 March 2016 as
the nominated completion date for the facility, the approved provider must--
(a) before 1 September 2013, provide an implementation plan to the
Implementation Committee, and
(b) before 1 March 2014 (and every 1 September
and 1 March after that date unless the fire sprinkler system has been
installed), provide a progress report to the Implementation Committee.
(2) An
implementation plan is to-- (a) specify details of the proposed installation
of the fire sprinkler system (including any approvals required for the
installation), and
(b) describe any work completed for the purposes of the
installation, and
(c) provide an estimate of the date by which the
installation will be completed, and
(d) specify the capital investment value
of installing the fire sprinkler system, and
(e) be in a form approved by the
Implementation Committee, and
(f) include any other information that the
Implementation Committee directs (in its approved form) is to be included in
the plan.
(3) A progress report is to-- (a) specify any changes to
information provided to the Implementation Committee in the implementation
plan or an earlier progress report, and
(b) be in a form approved by the
Implementation Committee.
(4) In this clause,
"approval" means an approval under the Act and includes a development consent,
a complying development certificate or any other certificate under Part 6 of
the Act.