(1) The maximum additional fee payable for a Part 3A application in respect of a critical infrastructure project is $50,000.
(2) If a project is declared to be a critical infrastructure project after the fee for the Part 3A application is paid or due for payment, the additional fee is payable within 14 days after the Planning Secretary notifies the proponent that the additional fee is payable.