(1) A reference in an environmental planning instrument to a comprehensive development application (as referred to in clause 92A immediately before the repeal of that clause by the Environmental Planning and Assessment Amendment (Planning Instruments and Development Consents) Regulation 2005 ) is taken to be a reference to a staged development application within the meaning of the Act.
(2) Section 83C(1) of the Act does not apply to any provision of an environmental planning instrument (as in force as at the commencement of this clause) that requires the making of a comprehensive development application that is taken to be a staged development application.