Conditions specified in this clause and Schedule 6 apply

3C.37 Conditions specified in this clause and Schedule 6 apply

(1) A complying development certificate for development under this code must be issued subject to the conditions specified in this clause and in Schedule 6.
Note :
"Complying development certificate" and
"environmental planning instrument" have the same meanings as they have in the Act.
(2) Waste management The following are conditions applying before works commence (in addition to those set out in Part 1 of Schedule 6)--
(a) A waste management plan for the work must be submitted to the principal certifying authority at least 2 days before work commences on the site.
(b) The waste management plan must--
(i) identify all waste (including excavation, demolition and construction waste materials) that will be generated by the work on the site, and
(ii) identify the quantity of waste material in tonnes and cubic metres to be--
(A) reused on-site, and
(B) recycled on-site and off-site, and
(C) disposed of off-site, and
(iii) if waste materials are to be reused or recycled on-site--specify how the waste material will be reused or recycled on-site, and
(iv) if waste materials are to be disposed of or recycled off-site--specify the contractor who will be transporting the materials and the waste facility or recycling outlet to which the materials will be taken.
(c) A garbage receptacle must be provided at the work site before works begin and must be maintained until the works are completed.
(d) The garbage receptacle must have a tight fitting lid and be suitable for the reception of food scraps and papers.
Note : A council has power under section 124 of the Local Government Act to make specific orders about the removal or keeping of waste.
(3) Maintenance of site The following is a condition applying during works (in addition to those set out in Part 2 of Schedule 6)--
Copies of receipts stating the following must be given to the principal certifying authority--
(a) the place to which waste materials were transported,
(b) the name of the contractor transporting the materials,
(c) the quantity of materials transported off-site and recycled or disposed of.
Note : Clause 9 of Schedule 6 sets out further conditions relating to maintenance of the site.
(4) Planting of trees The following is a condition applying as an operational requirement (in addition to those set out in Part 2 of Schedule 6)--
If the work relates to the erection of a new dwelling, a species of tree must be planted--
(a) in the area opposite the boundary to which the front of the dwelling house faces--that is capable of achieving a height of at least 8m at maturity, and
(b) in the area opposite the rear boundary of the dwelling house--that is capable of achieving a height of at least 5m at maturity.