ENVIRONMENTAL PROTECTION ACT 1994 - SECT 266
Deciding surrender application
266 Deciding surrender application
(1) The administering authority must decide to— (a) approve the surrender
application; or
(b) refuse the surrender application.
(2) Of the following
periods that apply to a surrender application, a decision under subsection (1)
about the application must be made within the later of the periods to end—
(a) if the administering authority requests further information under
section 265 (1) —40 business days after the further information is received
by the authority;
(b) if the administering authority does not request further
information under section 265 (1) —40 business days after the application is
made;
(c) if the environmental authority is for a resource activity and the
relevant tenure is an exploration permit or mineral development licence—60
business days after the relevant tenure ends;
(d) if the environmental
authority is for a resource activity and the relevant tenure is a mining lease
or petroleum lease—90 business days after the relevant tenure ends.