The progressive certification report must—
(a) contain the following information—(i) if a PRCP schedule applies for the relevant activities carried out in the proposed certified area—(A) information showing how the rehabilitation milestones and management milestones under the PRCP schedule have been achieved; and(B) information about the extent to which the relevant conditions stated in the PRCP schedule have been complied with;(ii) otherwise—information required under section 264 , as if a reference in the section to land were a reference to the proposed certified area; and
(b) include—(i) a map of an appropriate scale that shows the proposed certified area; and(ii) relevant information to locate the proposed certified area, including, for example, GPS information or a survey; and
(c) if progressive certification has previously been given for a relevant tenure for the environmental authority—(i) state when the certification was given; and(ii) identify the certified area the subject of the certification.