ENVIRONMENTAL PROTECTION ACT 1994 - SECT 616K
Plan of operations
616K Plan of operations
(1) This section applies if a plan of operations for a relevant mining lease
for a transitional authority (SAA) was in force under the
Mineral Resources Act immediately before the commencement.
(2) The plan of
operations— (a) is taken to be the plan of operations for the authority
submitted under section 233; and
(b) continues in force only until the
earlier of the following— (i) the end of the period, stated in the plan, to
which the plan applies;
(ii) the plan is replaced under section 235.
(2A)
Subsection (2)(a) is subject to subsection (2B) and the Mineral Resources Act,
section 735(4A).
(2B) The special agreement Act to which the authority
relates and the existing Act continue to apply for amending the plan of
operations as if the amending Act, other than for the insertion of
section 584, had not been enacted.
(3) Section 540(1)(e)(vi) does not apply
to a plan of operations that, under this section, is taken to be the plan of
operations for a transitional authority (SAA).
(4) For this section, the
relevant provisions of a mining plan approved under part 2 of the agreement
defined under the Mount Isa Mines Limited Agreement Act 1985 are taken to be a
plan of operations for each mining lease to which they relate.