Expiry of approval and extension of expiry day

153AF Expiry of approval and extension of expiry day

(1) An approval of a project as a private infrastructure facility expires on the day (the
"expiry day" ) that is 2 years after the gazette notice notifying the approval is published.
(2) Before an approval of a project as a private infrastructure facility expires—
(a) the proponent of the project may apply in writing to the Coordinator-General to extend the expiry day of the approval; or
(b) the Coordinator-General may extend the expiry day of the approval on his or her own initiative.
(3) An application under subsection (2) (a) must be accompanied by the fee prescribed under a regulation.
(4) If the Coordinator-General extends the expiry day of the approval, the Coordinator-General must give each of the following persons written notice of the extension—
(a) the proponent;
(b) the registered owner of the land on which the infrastructure facility is proposed to be located.
(5) If the Coordinator-General decides to refuse the application, the Coordinator-General must, within 28 days after making the decision, give the proponent written notice of the decision and the reasons for it.