STATE DEVELOPMENT AND PUBLIC WORKS ORGANISATION ACT 1971 - SECT 27A
Lapsing of declaration if EIS required
27A Lapsing of declaration if EIS required
(1) This section applies to a coordinated project if an EIS is required for
the project.
(2) The declaration for the project lapses if, within 18 months
of the terms of reference being finalised, the Coordinator-General has not,
under section 34A (1) (b) , accepted a draft EIS for the project as the final
EIS.
(3) Despite subsection (2) , if before the declaration lapses, the
Coordinator-General gives written notice to the proponent stating a later time
for the declaration to lapse, the declaration does not lapse until the later
time.