STATE DEVELOPMENT AND PUBLIC WORKS ORGANISATION ACT 1971 - SECT 34C
Requirement to give additional information
34C Requirement to give additional information
(1) This section applies if the Coordinator-General decides under section 34A
(1) (b) not to accept the draft EIS as the final EIS.
(2) If the notice given
under section 34B states that public notification of the additional
information is not required, the proponent must, within the period stated in
the notice, give the Coordinator-General a revised draft EIS.
(3) If the
notice given under section 34B states that public notification of the
additional information is required, the proponent must, within the period
stated in the notice— (a) comply with section 33 as if a reference in that
section to a draft EIS were a reference to the additional information stated
in the notice; and
(b) give the Coordinator-General a revised draft EIS.
(4)
Submissions about the additional information may be made under section 34 as
if the information were a draft EIS.
(5) If the Coordinator-General receives
a revised draft EIS under subsection (2) or (3) , sections 34A and 34B apply
to the revised draft EIS— (a) as if a reference in section 34A (1) to the
end of the submission period for the draft EIS were a reference to the day the
Coordinator-General receives the revised draft EIS; and
(b) as if a reference
in section 34A (1) (a) (ii) to a properly made submission for the draft EIS
were a reference to a properly made submission for the additional information;
and
(c) with any other necessary changes.