STATE DEVELOPMENT AND PUBLIC WORKS ORGANISATION ACT 1971 - SECT 34J
Giving notice of decision
34J Giving notice of decision
(1) The Coordinator-General must give the proponent written notice of the
Coordinator-General’s decision under section 34I .
(2) If the
Coordinator-General decides not to accept the draft IAR as the final IAR, the
notice must state the following— (a) the decision;
(b) the additional
information required;
(c) whether or not public notification of the draft IAR
as amended to include or attach the additional information (the
"revised draft IAR" ) is required;
(d) the period within which the
revised draft IAR must be given to the Coordinator-General.