In making the evaluation, the Coordinator-General must consider each of the following—
(a) the nature of the proposed change and its effects on the project;
(b) the project as currently evaluated under the Coordinator-General’s report for the EIS or IAR for the project;
(c) the environmental effects of the proposed change and its effects on the project;
(d) if, under section 35G , public notification was required—all properly made submissions about the proposed change and its effects on the project;
(e) if the change relates to a project for which an EIS was required—the material mentioned in section 34A (1) (a) to the extent the Coordinator-General considers it is relevant to the proposed change and its effects on the project;
(f) if the change relates to a project for which an IAR was required—the material mentioned in section 34I (1) (a) to the extent the Coordinator-General considers it is relevant to the proposed change and its effects on the project.