VEGETATION MANAGEMENT ACT 1999 - SECT 55AC
Approving restoration plan
55AC Approving restoration plan
(1) The chief executive must review a proposed restoration plan given to the
chief executive under section 55AB (1) and— (a) approve the plan; or
(b) if
the chief executive considers the plan does not adequately rectify the matter,
ask the person— (i) to consider or further consider any matter; and
(ii) to
amend the plan in the light of the person’s consideration or further
consideration; and
(iii) to give the amended plan to the chief executive for
approval; or
(c) ask the person to make stated changes to the plan and give
the amended plan to the chief executive for approval.
(2) The person must
give the amended restoration plan to the chief executive within 20 business
days after the chief executive makes a request under subsection (1) (b) or (c)
.
(3) The chief executive must review the amended restoration plan and
approve the plan or refuse to approve the plan.
(4) If the chief executive
approves the restoration plan under subsection (1) (a) or (3) , the chief
executive must give the person notice that the plan or amended plan is the
approved restoration plan.
(5) If the chief executive refuses to approve the
amended restoration plan, the chief executive must give the person— (a)
notice of the refusal; and
(b) an information notice about the decision to
refuse to approve the plan.
(6) If the person asks the chief executive to
prepare the restoration plan under section 55AB (3) , the plan prepared by the
chief executive is the approved restoration plan.