143A—Approval to carry out certain demolition work
(a) use
explosives on a demolition site; or
(b)
demolish a building or structure using mechanical equipment that needs to be
supported by any part of the building or structure,
the demolition must not be commenced before a proposed demolition work plan
has been submitted to the regulator, and the regulator has given approval to
the commencement of the work (and the regulator may attach conditions to any
such approval).
(2) A person must not
contravene or fail to comply with a condition imposed by the regulator under
subregulation (1).
Maximum penalty: $10 000.
(3) An approval given
by the Director under regulation 235 of the revoked Occupational Health,
Safety and Welfare Regulations 2010 that was in force immediately before
the revocation of those regulations will be taken to be approval given by the
regulator under this regulation and any condition attached to the approval
immediately before that revocation will be taken to be a condition of the
approval imposed by the regulator under subregulation (1).