312—High risk construction work—safe work method statements
The principal contractor for a construction project must take all reasonable
steps to obtain a copy of the safe work method statement relating to high risk
construction work before the high risk construction work commences.
Maximum penalty:
(a) In
the case of an individual—$3 600.
(b) In
the case of a body corporate—$18 000.
Expiation fee:
(a) In
the case of an individual—$432.
(b) In
the case of a body corporate—$2 160.
Note—
The WHS management plan contains arrangements for co-operation between persons
conducting a business or undertaking at the construction project workplace,
including in relation to the preparation of safe work method statements (see
regulation 309(2)(b) and (e)).