WORK HEALTH AND SAFETY REGULATIONS 2012 - REG 675T

675T—Review of survey plan

        (1)         The mine operator of a mine must review and as necessary revise the mine survey plan—

            (a)         if it no longer accurately reflects the workings that have been carried out at the mine or the workings that are proposed to be carried out at the mine; or

            (b)         if there are reasonable grounds to believe that the mine survey plan is not accurate; or

            (c)         at least once every 12 months.

Maximum penalty:

            (a)         in the case of an individual—$6 000;

            (b)         in the case of a body corporate—$30 000.

        (2)         Subregulation (1)(c) does not apply if the mining operations at the mine have been discontinued or suspended for more than 12 months.