(1) A major project impact statement is a statement that addresses the matters that are set out, in accordance with section 60ZM(4) , in the assessment criteria in relation to the major project, as matters that are required to be addressed in a major project impact statement.(2) If the Minister, under section 60TG(2) , amends a declaration of a major project so that the declaration also relates to an additional area of land, the major project impact statement in relation to the project that is subsequently provided under section 60ZS(1) may relate to the additional area of land, but if it does so, the major project impact statement is to include a statement (a) identifying the additional area of land; and(b) stating that the area of additional land was not included in the declaration of a major project as originally made.