Victorian Bills Explanatory Memoranda

[Index] [Search] [Download] [Bill] [Help]


Electricity Safety Amendment (Bushfire Mitigation Civil Penalties Scheme) Bill 2017

Electricity Safety Amendment (Bushfire
   Mitigation Civil Penalties Scheme)
                Bill 2017

                        Introduction Print


              EXPLANATORY MEMORANDUM


                              Clause Notes
Clause 1   sets out the main purpose of the Bill, which is to amend the
           Electricity Safety Act 1998 to impose additional bushfire
           mitigation requirements on major electricity companies, to
           enable the enforcement of those requirements through a civil
           penalty enforcement regime, and to provide for information
           notices and other matters.

Clause 2   provides for the commencement of the Bill. The Bill will
           come into operation on a day or days to be proclaimed, or on
           1 September 2017 if not proclaimed earlier.

Clause 3   provides for the Electricity Safety Act 1998 to be called the
           Principal Act in this Bill.

Clause 4   inserts new Part 10A into the Electricity Safety Act 1998.
           New Part 10A provides for additional bushfire mitigation
           requirements for major electricity companies. A definition of
           major electricity company is provided in section 3 of the
           Electricity Safety Act 1998.
           New section 120K of new Part 10A sets out definitions for the
           purposes of new Part 10A.
           New section 120L of new Part 10A provides for the meaning
           of complying substation for the purposes of new Part 10A.
           This definition is relevant to new section 120M, which requires
           major electricity companies to ensure that a sufficient number of


581228                               1       BILL LA INTRODUCTION 7/2/2017

 


 

zone substations in its supply network are complying substations so as to meet the prescribed number of allocated substation points for three separate periods. A zone substation is a complying substation if every polyphase electric line that originates from the substation has the required capacity. Definitions of zone substation, polyphase electric line, allocated substation point and required capacity are provided in new section 120K. New section 120M of new Part 10A provides for a new obligation for major electricity companies, which is to ensure that a sufficient number of zone substations in its supply network are complying substations so as to meet the prescribed number of allocated substation points for three separate periods. The prescribed number of allocated substation points will accrue in respect of a zone substation, when that zone substation is a complying substation. The regulations could prescribe a single point or multiple points for a zone substation. As per new section 120L, a zone substation is a complying substation if every polyphase electric line that originates from the substation has the required capacity. The required capacity is defined in new section 120K to mean the prescribed capacity in relation to a polyphase electric line in the event of a phase to ground fault. The prescribed capacity could, for example, be for the polyphase electric line to achieve a specified voltage or amperage reduction within a specified time in the event of a phase to ground fault. The three periods, and the points required to be met for each period, are set out in new section 120M(1)(a)-(c). • For the period from 1 May 2019 until 30 April 2021, or if Energy Safe Victoria specifies a later date following consultation with the Minister under new section 120X, until that date (the initial period), major electricity companies must achieve not less than 30 allocated substation points. • For the period from 1 May 2021 until 30 April 2023, or if Energy Safe Victoria specifies a later date following consultation with the Minister under new section 120X, until that date (the intermediate period), major electricity companies must achieve not less than 55 allocated substation points. 2

 


 

• On and after 1 May 2023 (or if Energy Safe Victoria specifies a later date following consultation with the Minister under new section 120X, that date), major electricity companies must ensure that all zone substations in their supply network are complying substations. The allocated substation points must continue to be met for the duration of the period. New sections 120M(1)(a) and (b) do not apply to a major electricity company that does not have a sufficient number of zone substations in its supply network to meet the total number of allocated substation points for those periods. New section 120M(3) provides that, the pecuniary penalty for contravening new section 120M is up to $2 000 000 for every point that is the difference between the allocated substation points that are met by complying substations and the points required to be met for the relevant period, plus a daily penalty of up to $5500 for each day that contravention continues after service on the major electricity company by Energy Safe Victoria of notice of that contravention. New section 120M does not apply to a major electricity company that is exempted from complying with new section 120M under an Order made under new section 120W, where the major electricity company complies with that Order (including by complying with any conditions to the Order). New section 120N of new Part 10A provides for new obligations for major electricity companies, which are-- • to cover or place underground each new electric line that meets the prescribed specification that it constructs within an electric line construction area; and • to cover or place underground each electric line that meets the prescribed specification, and which is reconstructed or substantially reconstructed within an electric line construction area, and which is of at least 4 consecutive spans or has conductors on at least 4 consecutive spans. New section 120N(5) provides for the meaning of cover in relation to an electric line. To cover an electric line means to install a system of insulation on a bare open wire in accordance 3

 


 

with the relevant major electricity company's accepted bushfire mitigation plan. Section 3 of the Electricity Safety Act 1998 provides a definition of accepted bushfire mitigation plan. Electric line construction area is defined in new section 120K to mean land delineated and shown on a prescribed plan. The pecuniary penalty for contravening new section 120N(1) or (2) is up to $350 000 for each kilometre or part of a kilometre of an electric line that is not covered or placed underground, plus a daily pecuniary penalty of up to $1000 for each day that contravention continues after service on the major electricity company by Energy Safe Victoria of notice of that contravention. New section 120N does not apply to a major electricity company that is exempted from complying with new section 120N under an Order made under new section 120W, where the major electricity company complies with that Order (including by complying with any conditions to the Order). New section 120O of new Part 10A provides for a new obligation for major electricity companies, which is to install an Automatic Circuit Recloser for each SWER line in its supply network before 1 January 2021 (or if Energy Safe Victoria specifies a later date following consultation with the Minister under new section 120X, by that date). Automatic Circuit Recloser is defined in new section 120K to mean a device that is capable of performing certain functions in relation to a SWER line. SWER line is defined to mean a single wire earth return electric line. The penalty for contravening new section 120O(1) is up to $50 000 for each contravention, plus a daily penalty of up to $150 for each day that contravention continues after service on the major electricity company by Energy Safe Victoria of notice of that contravention. New section 120O does not apply to a major electricity company that is exempted from complying with new section 120O under an Order made under new section 120W, where the major electricity company complies with that Order (including by complying with any conditions to the Order). New section 120P of new Part 10A requires a major electricity company to give a written report to Energy Safe Victoria before 1 August each year, which includes certain information. 4

 


 

A major electricity company's report under new section 120P must-- • include details of work carried out, and plans for future work, in respect of the obligations under new sections 120M, 120N and 120O; • include details of the location of each zone substation, electric line and Automatic Circuit Recloser on which works have been carried out; • be in a form and include the information specified by Energy Safe Victoria; • be approved by the board of a major electricity company; and • be published by Energy Safe Victoria on its Internet site. The penalty for contravening new section 120P(1) is up to $10 000 for each contravention, plus a daily penalty of up to $1000 for each day that contravention continues after service on the major electricity company by Energy Safe Victoria of notice of that contravention. New section 120Q of new Part 10A requires a major electricity company to obtain, on the request of Energy Safe Victoria and at the intervals determined by Energy Safe Victoria, an independent audit of the major electricity company's compliance with new sections 120M, 120N, 120O or 120P. A major electricity company that is required to obtain an audit under new section 120Q must establish to the satisfaction of Energy Safe Victoria that each person undertaking an audit has the necessary competence, ability and access to information to enable an independent audit. Further, the costs of such an audit must be borne by the major electricity company. The penalty for contravening new section 120Q(1) is up to $50 000 for each contravention, plus a daily penalty of up to $5000 for each day that contravention continues after service on the major electricity company by Energy Safe Victoria of notice of that contravention. 5

 


 

New section 120R of new Part 10A provides for the Minister or Energy Safe Victoria to bring civil proceedings in respect of a civil penalty provision. Civil penalty provision is defined in new section 120K to mean new section 120M, 120N, 120O, 120P or 120Q. New section 120S of new Part 10A clarifies that enforcement proceedings under new section 120R are civil proceedings, not criminal proceedings. Subsections (a)-(f) provide that criminal proceedings do not lie against a person by reason only that the person has contravened or attempted to contravene a civil penalty provision, or has engaged in other acts and practices relating to contraventions of civil penalty provisions. New section 120T of new Part 10A sets out the basis upon which civil penalty provisions may be enforced by the Minister or Energy Safe Victoria. Subsection (1) provides that the Minister or Energy Safe Victoria may apply to the Supreme Court (the Court) for an order in respect of the doing of a thing referred to in subsection (3). Subsection (2) provides for the Court to make orders for major electricity companies to pay pecuniary penalties to the Minister if satisfied that a thing specified in subsection (3) has been done. Subsection (3) lists the matters which give rise to a Court order for payment of a pecuniary penalty to the Minister. Subsection (4) sets out the matters that the Court may have regard to in determining the amount of the pecuniary penalty. New section 120U of new Part 10A provides that pecuniary penalties received by the Minister are to be paid into the Consolidated Fund. New section 120V of new Part 10A empowers the Court to grant declaratory relief in relation to contraventions of civil penalty provisions upon the application of the Minister or Energy Safe Victoria. Subsection (1) allows the Court to make an order declaring whether or not a major electricity company has contravened a civil penalty provision on the application of the Minister or Energy Safe Victoria. Subsection (2) provides for the requirements that may be included in an order that declares the major electricity company to have contravened a civil penalty provision. 6

 


 

New section 120W of new Part 10A provides for the Governor in Council, on the recommendation of the Minister, to exempt a major electricity company from complying with new section 120M, 120N or 120O. An exemption may be of general or specific application, may specify conditions, and is subject to the terms and conditions specified in the Order. New section 120X of new Part 10A provides for Energy Safe Victoria to specify later dates by which a major electricity company must comply with the obligations in new sections 120M(1) and 120O(1), on the application of a major electricity company. A request by a major electricity company under this section must set out the reasons for the request. Before specifying an alternative period or date on the application of a major electricity company, Energy Safe Victoria must consult with the Minster. New section 120Y of new Part 10A provides for Energy Safe Victoria to require a major electricity company to provide certain information for the purposes of verifying a report under new section 120P or an independent audit under new section 120Q. A notice issued under this section must specify the information required by Energy Safe Victoria, the format in which it is to be given, and the date by which it must be given. New section 120Y does not require a major electricity company to give information that is the subject of legal professional privilege or client legal privilege. However it is not a lawful excuse for a major electricity company to fail to comply with a notice on the ground of any duty of confidence. The penalty for contravening new section 120Y is 200 penalty units. New section 120Z of new Part 10A provides for Energy Safe Victoria to conduct, or cause to be conducted, an audit of a major electricity company's compliance with the civil penalty provisions. Clause 5 amends section 141AB of the Electricity Safety Act 1998 to allow Energy Safe Victoria to require a person to give information under that section for a broader range of purposes. 7

 


 

The amended section 141AB(1) allows Energy Safe Victoria to require a person to give certain information that it reasonably requires and which relates to a distribution company's compliance with Divisions 1A, 2 and 4 of Part 8, and Part 10 of the Electricity Safety Act 1998. As unamended, section 141AB(1) only allows Energy Safe Victoria to require this information for the purpose of preparing annual reports. Following amendment by this clause, section 141AB(1) will allow Energy Safe Victoria to require this information for the more general purpose of verifying the performance of distribution companies in complying with Divisions 1A, 2 and 4 of Part 8, and Part 10 of the Electricity Safety Act 1998. Clause 6 makes a consequential amendment to the heading of Division 2A of Part 10 of the Electricity Safety Act 1998. This amendment is consequential to the insertion of new Part 10A by clause 4. Clause 7 provides for the automatic repeal of this amending Act on 1 September 2018. The repeal of this Act does not affect in any way the continuing operation of the amendments made by this Act (see section 15(1) of the Interpretation of Legislation Act 1984). 8

 


 

 


[Index] [Search] [Download] [Bill] [Help]