Victorian Current Acts

[Index] [Table] [Search] [Search this Act] [Notes] [Noteup] [Previous] [Next] [Download] [Help]

BUILDING ACT 1993 - SECT 205HA

Relevant building surveyor must refuse permit in certain circumstances

Without limiting the circumstances in which a relevant building surveyor may refuse to issue a building permit under Part 3, the relevant building surveyor must refuse an application for a building permit if the relevant building surveyor is satisfied—

        (a)     that the contract price for the building work specified in the application is substantially lower than the price normally payable under contracts for building work of that kind; or

        (b)     that the application—

S. 205HA(b)(i) amended by Nos 43/2019 s. 17, 31/2020 s. 57C.

              (i)     does not comply with section 205H(1)(b), (1AA)(c) or (1A)(b); or

              (ii)     contains a statement about the cost of the building work that is false or misleading in a material particular.

S. 205I inserted by No. 34/2013 s. 4, substituted by No. 43/2019 s. 18.