BUILDING ACT 1993 - SECT 43

Decision on application for occupancy permit

    (1)     The relevant building surveyor must decide an application for an occupancy permit under this Division by—

        (a)     issuing the permit; or

        (b)     issuing the permit with conditions; or

        (c)     refusing the permit.

    (2)     The regulations may prescribe a time within which the relevant building surveyor must decide an application for an occupancy permit.

S. 43(3) amended by No. 21/2017 s. 99.

    (3)     The relevant building surveyor is taken to have refused an occupancy permit if the application is not decided within the prescribed time.

S. 44 substituted by No. 75/1998 s. 6.