Victorian Current Acts

[Index] [Table] [Search] [Search this Act] [Notes] [Noteup] [Previous] [Next] [Download] [Help]

DOMESTIC BUILDING CONTRACTS ACT 1995 - SECT 23

Builder must supply evidence of cost of prime cost items and provisional sums

A builder must give the building owner a copy of any invoice, receipt or other document that shows the cost to the builder of any prime cost item, or that relates to any provisional sum, in a domestic building contract and must do so as soon as practicable after receiving the invoice, receipt or document.

Penalty:     20 penalty units.

Division 5—Other matters



AustLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback