(1) If an application is made for a building permit for the construction of a building, the relevant building surveyor may require a report from the relevant electricity supply authority as to whether an electricity sub-station is necessary on the allotment and, if so, the size and location of the sub-station.
(2) This regulation does not apply to the construction of a Class 1 or 10 building.