Building surveyor to notify chief officer of issue of certificates of final inspection

    (1)     If a certificate of final inspection is issued for building work in respect of which there is a requirement under these Regulations or any previous corresponding regulations that the transmission signal of an alarm be connected to a fire station or other approved monitoring service, the relevant building surveyor must notify the chief officer within 10 days after the issue of the certificate that—

        (a)     the certificate has been issued; and

        (b)     the required connection has been made.

    (2)     If a certificate of final inspection is issued for building work for which an occupancy permit is not required and the chief officer was a reporting authority in respect of the application for the relevant building permit, the relevant building surveyor must notify the chief officer within 10 days after the issue of the certificate that the certificate has been issued.

__________________



AustLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback