Record of pile-driving

Any person installing piles must—

        (a)     keep a record of all pile-driving operations undertaken during the construction including any determination of allowable loadings; and

        (b)     make the records available for inspection by the relevant building surveyor during the progress of the pile-driving operations; and

        (c)     within 28 days of the completion of the pile-driving operations forward the complete records of the pile-driving operations to the relevant building surveyor.

Penalty:     10 penalty units.