Sch. 3
TIME LIMITS FOR BUILDING PERMIT APPLICATIONS
Column 1 |
Column 2 |
Column 3 |
Column 4 |
Column 5 |
Item number |
Matter |
Class 1 or 10 buildings |
Class 2–9 buildings |
Act provision |
1 |
Relevant building surveyor to give reporting authority a copy of an application |
3 business days |
5 business days |
Schedule 2 clause 4(2) |
2 |
Time after receipt of copy of application for reporting authority to report on and consent to application |
10 business days |
10 business days |
Schedule 2 clause 6 |
3 |
Time after receipt of copy of application for reporting authority to report on and consent to an application for a matter under Division 2 of Part 4 and regulation 424 |
15 business days |
Not applicable |
Schedule 2 clause 6 |
4 |
Time after receipt of copy of application for responsible authority to report on and consent to application |
15 business days |
15 business days |
Schedule 2 clause 6A |
Column 1 |
Column 2 |
Column 3 |
Column 4 |
Column 5 |
Item number |
Matter |
Class 1 or 10 buildings |
Class 2–9 buildings |
Act provision |
5 |
Time for relevant building surveyor to decide application after all reporting authority reports and consents are received or the end of the relevant time prescribed for the supply of those reports and consents whichever is the earlier |
10 business days |
15 business days |
section 19 |
6 |
Further time for applicant to supply a report and consent of a reporting authority to relevant building surveyor |
3 calendar months |
6 calendar months |
Schedule 2 clause 5(4) |
Sch. 3
__________________