BUILDING REGULATIONS 2006 (SR NO 68 OF 2006) - SCHEDULE 6

SCHEDULE 6

Sch. 6

Regulation 1004

TIME LIMITS FOR OCCUPANCY PERMIT APPLICATIONS

Column 1

Column 2

Column 3

Column 4

Column 5

Item number

Matter

Class 1 building

Class 2–9 buildings

Act provision

1

Relevant building surveyor to give reporting authority copy of an application

3 business days

5 business days

Schedule 2 clause 4(2)

2

Time after receipt of copy of application for reporting authority to report on and consent to an application

5 business days

10 business days

Schedule 2 clause 6

3

Time for relevant building surveyor to decide application after all reporting authority reports and consents are received or the end of the relevant time prescribed for the supply of those reports and consents, whichever is earlier

2 business days

5 business days

section 43 or section 56