The relevant building surveyor may require all or any of the following information to be submitted in relation to an application for a building permit and the allotment to which it relates—
(a) details of measures for the protection of the public under regulation 116 ;
(b) documentary evidence to support the use of a material, form of construction or design in a form referred to in clause A2.2 of the BCA Volume One or clause 1.2.2 of the BCA Volume Two;
(c) a survey plan of existing site conditions prepared by a licensed surveyor within the meaning of the Surveying Act 2004 ;
(d) if the allotment is under the operation of the Transfer of Land Act 1958 , a copy of the certificate of title to the allotment;
(e) evidence of ownership of the allotment or evidence that a contract has been entered into pursuant to section 9AA of the Sale of Land Act 1962 in relation to the allotment;
(f) evidence that each building practitioner to be engaged in, or to carry out, the building work—
(i) holds a building practitioner's certificate issued by the Authority under the Act; or
(ii) is an architect registered under the Architects Act 1991 or is an insured architect (as the case requires);
(g) details as to whether the allotment is—
(i) in an area that is liable to flooding within the meaning of regulation 5(2) ; or
(ii) in an area that is designated under regulation 150 as an area in which buildings are likely to be subject to attack by termites; or
(iii) in an area designated under regulation 152 as likely to be subject to significant snowfalls; or
(iv) in an area that is a designated bushfire prone area as determined under regulation 155; or
(v) designated land;
(h) details as to whether an approved building envelope applies to the allotment or to an adjoining allotment;
(i) a list of any essential safety measures to be provided in the building or place of public entertainment to which the building permit relates.
Division 3—Report or consent of reporting authorities