BUILDING REGULATIONS 2018 (SR NO 38 OF 2018) - REG 29

Additional information to accompany application for permit

The relevant building surveyor may require all or any of the following information to be submitted in relation to an application for a building permit and the allotment to which it relates—

        (a)     details of measures for the protection of the public under regulation 116 ;

        (b)     documentary evidence to support the use of a material, form of construction or design in a form referred to in clause A2.2 of the BCA Volume One or clause 1.2.2 of the BCA Volume Two;

        (c)     a survey plan of existing site conditions prepared by a licensed surveyor within the meaning of the Surveying Act 2004 ;

        (d)     if the allotment is under the operation of the Transfer of Land Act 1958 , a copy of the certificate of title to the allotment;

        (e)     evidence of ownership of the allotment or evidence that a contract has been entered into pursuant to section 9AA of the Sale of Land Act 1962 in relation to the allotment;

        (f)     evidence that each building practitioner to be engaged in, or to carry out, the building work—

              (i)     holds a building practitioner's certificate issued by the Authority under the Act; or

              (ii)     is an architect registered under the Architects Act 1991 or is an insured architect (as the case requires);

        (g)     details as to whether the allotment is—

              (i)     in an area that is liable to flooding within the meaning of regulation 5(2) ; or

              (ii)     in an area that is designated under regulation 150 as an area in which buildings are likely to be subject to attack by termites; or

              (iii)     in an area designated under regulation 152 as likely to be subject to significant snowfalls; or

              (iv)     in an area that is a designated bushfire prone area as determined under  regulation 155; or

              (v)     designated land;

        (h)     details as to whether an approved building envelope applies to the allotment or to an adjoining allotment;

              (i)     a list of any essential safety measures to be provided in the building or place of public entertainment to which the building permit relates.

        Division 3—Report or consent of reporting authorities



AustLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback