Information the relevant building surveyor must give to the Authority

    (1)     A relevant building surveyor must within 7 days after the end of each month give to the Authority in a form approved by the Authority—

        (a)     details of all permits and certificates of final inspection issued by the relevant building surveyor during that month; and

        (b)     the following details relating to the building work to which each building permit issued by the relevant building surveyor during that month applies, including—

              (i)     whether any of the building work will be carried out on an allotment in a designated bushfire prone area determined under regulation 155 and the applicable bushfire attack level determined for that allotment;

              (ii)     whether the building work relates to a change of use of a building;

              (iii)     whether the building work involves the construction of a private bushfire shelter.

    (2)     In addition to the details under subregulation (1), on and from 1 July 2019, the relevant building surveyor must within 7 days after the end of each month give to the Authority in a form approved by the Authority the following details relating to the building work to which each building permit issued by the relevant building surveyor during that month applies—

        (a)     whether an occupancy permit is required in relation to the building work;

        (b)     the mandatory notification stages for the building work set out under Part 12;

        (c)     whether the building work is to be carried out on land that is subject to a determination under regulation 64(1);

        (d)     whether any exemption from, or consent to partial compliance with, certain requirements of these Regulations relating to the building work has been given by the relevant building surveyor under regulation 229(2), 231(2), 233(3) or 234(2);

        (e)     whether the building work involves the construction of a swimming pool or spa or an associated safety barrier;

        (f)     whether the relevant building surveyor determined under regulation 111(2) that protection work is required in relation to the building work.

    (3)     The relevant building surveyor must, within 7 days after the end of each month, give to the Authority in a form approved by the Authority the following details in relation to any building permit issued by the relevant building surveyor—

        (a)     any lapse of a building permit during that month;

        (b)     details to the knowledge of the relevant building surveyor of any building work to which the permit applies that is commenced, completed or abandoned during that month.

    (4)     In addition to the details under subregulation (3), on and from 1 July 2019, the relevant building surveyor must within 7 days after the end of each month give to the Authority in a form approved by the Authority the following details relating to any building permit issued by the relevant building surveyor—

        (a)     any extension granted during that month by the relevant building surveyor under regulation 59 to the commencement date or completion date of the building work to which the permit applies and the new dates;

        (b)     any inspection of building work to which the permit applies at a mandatory notification stage under section 34 of the Act;

        (c)     any determination by the relevant building surveyor that protection work is required in relation to building work to which the permit applies under regulation 111(3).



AustLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback