(1) If the Commission
under section 143 refuses to approve a plan of subdivision and the applicant
for approval concerned is dissatisfied with the refusal, that applicant may
within 28 days of being notified of the refusal request in writing the
Commission to reconsider the refusal.
(2) On receiving a
request under subsection (1), the Commission, by notice in writing served on
the person who made that request, may —
(a)
approve the plan of subdivision; or
(b)
again refuse to approve the plan of subdivision; or
(c)
approve the plan of subdivision and require the applicant for approval to
comply with such conditions as the Commission thinks fit before the diagram or
plan of survey will be endorsed with the approval of the Commission.