708 Time limits for claiming compensation

A claim for compensation under this part must be given to the local government--

(a) if the entitlement to claim the compensation is under section 704(1)--within 6 months after the day the application mentioned in section 704(1)(d) is refused or approved in part, or subject to conditions or approved both in part and subject to conditions; or
(b) if the entitlement to claim the compensation is under section 704(2)--within 6 months after the day the request for compliance assessment mentioned in section 704(2)(d) is approved subject to conditions; or
(c) if the entitlement to claim the compensation is under section 704(3)--within 6 months after the day the request mentioned in section 704(3)(b) is refused; or
(d) if the entitlement to claim the compensation is under section 705--within 2 years after the day the change came into effect; or
(e) if the entitlement to claim the compensation is under section 707--at any time after the day the certificate is given.