DOMESTIC BUILDING CONTRACTS ACT 1995 - SECT 49L

Decision of chief dispute resolution officer on request

    (1)     The chief dispute resolution officer must consider a request under section 49J and, within 5 business days after receiving the request, decide—

        (a)     to amend or cancel the dispute resolution order; or

        (b)     to refuse to amend or cancel the dispute resolution order.

    (2)     The chief dispute resolution officer is taken to have refused the request if the chief dispute resolution officer does not make a decision within 5 business days after the request.

S. 49M inserted by No. 15/2016 s. 6, substituted by No. 47/2019 s. 21.