DOMESTIC BUILDING CONTRACTS ACT 1995 - SECT 49M

Matters to be considered in deciding on request

In making a decision on a request under section 49J, the chief dispute resolution officer

        (a)     must consider the extent to which any defective or incomplete domestic building work specified in the dispute resolution order has been rectified or completed; and

        (b)     may consider—

              (i)     the conduct of the parties; and

              (ii)     if section 49J(2) applies—any change in the nature of the dispute or the circumstances of the parties since the assessor gave a copy of the assessor's report to the chief dispute resolution officer under Division 5; and

              (iii)     any other matter the chief dispute resolution officer considers relevant.

S. 49N inserted by No. 15/2016 s. 6.